Section A: Executive Project Contractual Risk Health Check
The 15-Question Construction Project Contractual Risk Health Check is designed for Managing Directors, Project Directors, Commercial Directors and senior management. Answer each question honestly to assess whether your project is contractually controlled, vulnerable, or in need of immediate management attention.
Question 1
Are variations being carried out before written confirmation has been received from the Engineer or Contract Administrator?
YesPartlyNo
Why this matters: Verbal variations without written confirmation create unvalued work. Under the Four-Corner Rule, if the variation is not documented within the contract, payment entitlement may be lost entirely.
Question 2
Is the total value of unvalued variations reported to senior management on a monthly basis?
YesPartlyNo
Why this matters: Unreported variation values create a false picture of project profitability. By the time the exposure is identified, the cumulative effect on cash flow may be irreversible.
Question 3
Does the project have a proper contractual notice calendar with all critical deadlines identified and assigned?
YesPartlyNo
Why this matters: Failure to issue notices within contractual time limits can extinguish entitlement entirely. Time bars under FIDIC Sub-Clause 20.1 (1999) and similar provisions are strictly enforced.
Question 4
Has the project team been briefed on all amendments made to the standard contract form (e.g., FIDIC, PAM, JKR) in the particular project contract?
YesPartlyNo
Why this matters: Standard form amendments often shift risk materially. If the team assumes standard form protection without reviewing the particular amendments, critical entitlements may be lost.
Question 5
Are payment deductions and under-certifications being formally challenged within the contractual time limits?
YesPartlyNo
Why this matters: Silence on payment deductions may be construed as acceptance. Under most standard forms, failure to give notice of dissatisfaction within the stated period results in the determination becoming final and binding.
Question 6
Are delay events being recorded contemporaneously with supporting records, or only after the fact?
YesPartlyNo
Why this matters: Delay records prepared after the event are inherently less credible. Contemporaneous records are the strongest evidence in delay analysis and dispute resolution.
Question 7
Do monthly management reports show the contractual and commercial health of the project, not merely the physical progress?
YesPartlyNo
Why this matters: Physical progress tells you what has been built. Contractual and commercial health tells you whether you will be paid for what has been built and whether you are exposed to claims.
Question 8
Are verbal instructions from the Engineer, Employer or Project Manager always confirmed in writing with a request for written instruction?
YesPartlyNo
Why this matters: Verbal instructions create ambiguity. If the instruction is disputed later, the absence of written confirmation leaves the contractor without contractual evidence.
Question 9
Are contractual time bars being actively monitored with a system that alerts the responsible person before deadlines expire?
YesPartlyNo
Why this matters: Time bars are strictly enforced across Common Law, Civil Law and Sharia jurisdictions. Missing a notice deadline can extinguish entitlement regardless of its merit.
Question 10
Has responsibility for issuing each category of contractual notice been clearly assigned to a named individual?
YesPartlyNo
Why this matters: When everyone is responsible, no one is responsible. Unassigned notice obligations are the most common cause of missed deadlines on construction projects.
Question 11
Do your variation records contain the instruction, costs, resources, dates and supporting evidence for each variation?
YesPartlyNo
Why this matters: Incomplete variation records cannot support a claim. The burden of proof rests on the party making the claim, and the records must demonstrate both entitlement and quantum.
Question 12
Are Extensions of Time (EOT) being prepared and submitted before contractual deadlines expire?
YesPartlyNo
Why this matters: Late EOT submissions may be time-barred under many standard forms. Even where the delay event is genuine, the contractor may lose entitlement by failing to comply with procedural requirements.
Question 13
Are payment claims fully supported with the required documentation and submitted strictly in accordance with the contract requirements?
YesPartlyNo
Why this matters: Payment claims that do not comply with contractual requirements may be rejected on procedural grounds, creating cash flow pressure and potential escalation to dispute.
Question 14
Are unresolved claims and contractual risks being escalated to senior management before they become disputes?
YesPartlyNo
Why this matters: Early escalation enables strategic decision-making. By the time a claim becomes a dispute, the options for commercial resolution are narrower and more expensive.
Question 15
Does the project have a properly organised contractual and claims record system that enables retrieval of documents within minutes?
YesPartlyNo
Why this matters: Disputes are won and lost on evidence. A disorganised record system means that valid claims cannot be substantiated and invalid claims cannot be refuted.
Your Project Risk Score
Count your answers and assess your overall contractual risk position:
Green — Contractually Controlled: Most answers are "No" (meaning the risks are addressed). Your project has adequate contractual controls.
Amber — Contractually Vulnerable: A significant number of "Partly" answers. Your project has gaps that could be exploited in a dispute.
Red — Immediate Management Attention Required: Multiple "Yes" answers indicating active risk exposure. Immediate action is recommended.